September 2023 | Begin relocation of collections. |
August 2023 |
Building completion. Staff training. |
May - July 2023 |
Shelving installation. Outside painting and panel installation. Landscaping. |
April 2023 |
Film vault installation. |
March 2023 | Concrete floors poured. |
January 2023 | Temporary heating and lighting installation. |
December 2022 | Roof installation. |
1 November - 14 November | Installation of exterior wall panels. |
16 September | Iron Mountain staff to visit DLD and LCSF site and meet with staff. |
22 August - 30 September | Installation of concrete footings. |
18 July - 19 August |
438 geo-piles foundation piers installed. |
6 June |
DEW begins on-site mobilization. |