Library Collections & Services Facility

2023

September 2023 Begin relocation of collections.
August 2023

Building completion.

Staff training.

May - July 2023

Shelving installation.

Outside painting and panel installation.

Landscaping.

April 2023

Film vault installation.

March 2023 Concrete floors poured.
January 2023 Temporary heating and lighting installation.

2022

December 2022 Roof installation.
1 November - 14 November Installation of exterior wall panels.
16 September Iron Mountain staff to visit DLD and LCSF site and meet with staff.
22 August - 30 September Installation of concrete footings.

18 July - 19 August

438 geo-piles foundation piers installed.

6 June

DEW begins on-site mobilization.