2023

Fall 2023                       Relocation of materials and opening of the new facility.

2022

January 2023 Window installation. Temporary heating and lighting installation.
December 2022 Roof installation.
1 November - 14 November Installation of exterior wall panels.
16 September Iron Mountain staff to visit DLD and LCSF site and meet with staff.
22 August - 30 September Installation of concrete footings.

18 July - 19 August

438 geo-piles foundation piers installed.

6 June

DEW begins on-site mobilization.